Project Stakeholder Management

1. Identify Stakeholders


2. Plan Stakeholder Management


3. Manage Stakeholder Engagement


4. Control Stakeholder Engagement



Question - 1

You are developing strategies to effectively engage stakeholders throughout the project life cycle. What is process you are working on ?

A. Plan Stakeholder Management

B. Identify Stakeholders

C. Manage Stakeholder Engagement

D. Control Stakeholder Engagement


A is the correct answer. Plan Stakeholder Management is the process to develope strategy to effectively engage stakeholders throughout the project life cycle.


Question - 2

The key benefits of ____________ process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and environment changes.

A. Plan Stakeholder Management

B. Identify Stakeholders

C. Manage Stakeholder Engagement

D. Control Stakeholder Engagement


D is the correct answer. The key benefits of Control Stakeholder Engagement process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and environment changes.